How to find critical path, free float, total float
ES(Early Start) = The earliest date activity can start
EF(Early Finish) = The earliest date activity can finish
LS(Late Start) = The latest date activity can start without delaying project completion date
LF(Late Finish) = The latest date activity can finish without delaying project completion date
(D=duration)
EF = ES + D
LF = LS + D
Free Float/Path Float/Slack = LF - EF
Total Float = LF - ES - D